After this module you should be able to
- Estimate the need for hemodialysis in a catchment area and the travel burden patients carry today.
- Describe the local market without assuming that more units always means better access.
- Test a plan under bad assumptions with sensitivity analysis and the break-even calculator.
- Commit money in stages, through four investment gates.
The big picture, in plain words
The picture has a limit. A sailor can turn back when the weather changes. A dialysis unit that opens has patients who cannot be told to come back next season. That is why the forecast must include the bad case, and why money should be released in stages.
Figure 1 · Key terms for this module
Your work here is honest: estimate need, map travel, find the assumption that can sink you, and refuse to open a unit you cannot staff.
Case: Forty kilometers
Mrs. Teresita Manalo, a retired teacher, and her two children want to open a 10-station unit in a municipality in Nueva Ecija. The nearest unit is 40 kilometers away, and patients ride a tricycle and a bus for about ninety minutes each way, three times a week. The family’s plan assumes 60 patients by month six, claims paid in 30 days, and two nurses hired from the town.
Their spreadsheet shows a profit from month four. Their bank asks for a feasibility memo.
Before reading on, decide:
- Which assumption worries you most?
- How would you test the plan?
- What should happen before any building work starts?
Keep your answers in mind. The lesson gives you what you need, and the case review near the end shows one sound response.
Estimating need and travel
Start with people, not chairs. Ask the nearest units, the provincial hospital’s nephrologist, and local physicians how many patients from your area already dialyze elsewhere, how many are close to starting, and how long they travel. Philippine patients face long distances, out-of-pocket costs, and gaps in services, and travel time itself is a burden that leads to missed sessions.1
Convert need into station-sessions. Each patient on three sessions a week needs three station-sessions. With two shifts a day, six days a week, one station gives twelve station-sessions a week, enough for four patients with no slack. Keep slack for make-up sessions, as Module 2 explained.
Reading the local market
More units do not always mean more choice. In the United States, a decade of consolidation left local dialysis markets highly concentrated, with an average Herfindahl-Hirschman Index (HHI) of 0.46, where 1 means a single provider; patients’ choices did not shrink only because new facilities kept opening to meet demand.2 The Philippine market is different, but the lesson transfers. Ask who already serves your area, whether they are full, and whether your unit adds access or only divides the same patients.
A unit that only divides patients will compete on inducements, and Module 19 explains why that harms them. A unit that shortens a ninety-minute trip to twenty minutes adds real access.
Find the assumption that can sink you

Every plan rests on a few assumptions: sessions per month, net revenue per session, days to collect, staff cost, supply prices, and rent. Change each one to a realistic bad value, one at a time, and see how far the result moves. The assumption that moves it most is the one to test hardest.
Worked example (fictional). Fixed costs are 630,000 pesos a month. Net facility revenue is 6,000 pesos a session after the professional fee share and deductions, and variable cost is 3,900 pesos. Contribution is 2,100 pesos a session, so break-even is 630,000 ÷ 2,100 = 300 sessions a month: 25 patients on three sessions a week. The family’s 60 patients would be comfortably above break-even, but only if they arrive. At 30 patients in month six, the unit earns a small margin; at 20, it loses money every month.
Then test cash. If claims take 75 days instead of 30, the unit must finance about two and a half months of revenue before cash catches up. Module 17 shows how to size that.
Four gates before you build

Release money in stages. Each gate opens only when its evidence exists.
| Gate | Evidence needed |
|---|---|
| 1. Need and travel | Named sources for patient numbers; travel times; letters of interest from referring physicians |
| 2. Staff and water | A clinical head who has agreed in principle; a realistic hiring plan for nurses; a water source tested for treatment design |
| 3. Money under the bad case | Break-even, cash runway, and loan coverage under low volume and slow collection |
| 4. Permits and accreditation path | Permit to construct, design reviewed against Department of Health (DOH) guidelines, and a timeline for license and accreditation |
Gate 2 is the one families most often skip. A building without nurses, or with water that cannot be treated to standard, is not a unit.
Back to the case: Forty kilometers
The worrying assumptions. Sixty patients by month six and claims paid in 30 days. Both are optimistic. Two nurses from the town are also unlikely to cover two shifts at the DOH limit.
The test. Run the break-even calculator at 20, 30, and 60 patients and the cash calculator at 75 days to collect. Ask the bank for a facility that survives the bad case.
Before building. Pass Gate 1 with real patient counts, Gate 2 with a clinical head and a staffing plan that meets the license, and Gate 3 with a funded reserve. Only then sign the construction contract.
Skills checklist: Feasibility memo with sensitivity and investment gates
Write a two-page feasibility memo for a fictional site and present it to a mock lender. Your preceptor rates each step as satisfactory, needs practice, or not observed. Steps marked Critical must all be satisfactory before sign-off. This checklist supports supervised learning; your unit’s own procedure and competency form are the authority. A printable version of every checklist is on the trainer page.
- Estimates need from named sources and states travel times.
- Converts patients into station-sessions with make-up slack.
- Runs break-even and cash for a base case and a bad case.
- Names the assumption with the widest effect and how it will be tested.
- CriticalRefuses to release construction money before staffing and water are secured.
- Lists the four gates with the evidence each requires.
Check your understanding
Each visit draws 5 questions at random from this module’s 6-question bank. Choose the single best answer for each, then select Check answers; an explanation appears under the best answer. Select New set of questions for a different mix. A good target is 4 of 5 on two different sets. Nothing you select is sent anywhere; scoring happens in your browser.